Solar PV Inspection and Maintenance mobile form preview
Energy & EnvironmentalElectrical Mobile form 4 sections · 35 questions Free

Solar PV Inspection and Maintenance template

Periodic inspection of a solar PV system: array condition, DC isolators, inverter, string readings and generation.

Use this template free

Opens in a free trial with this form ready to use.

Download printable PDF (86 KB)
Relates to

BS EN 62446-1; MCS

This template is provided as a starting point only. pro-Forms accepts no liability for the accuracy or suitability of its forms. Check every form with a suitably qualified person before using it in a live environment.

About this template

Periodic inspection and maintenance of a solar PV system. Record the system size, inverter and number of strings, then check the modules, mounting, cabling and connectors, DC and AC isolators, inverter fault codes, labelling, any battery storage, monitoring and changes in shading.

String readings record open-circuit voltage, short-circuit current and insulation resistance, alongside the generation meter reading, recommendations and photos.

What's on this form

Every field in the template, grouped as it appears on the phone. Required fields are marked *.

1. System

  • Customer name * Text
  • Site name Text
  • Site address Paragraph
  • Job reference Text
  • Date of visit * Date
  • Time on site Time
  • Time off site Time
  • System size (kWp) * Text
  • Inverter make / model Text
  • Number of strings Text

2. Inspection

  • Modules clean and undamaged * Pass / Fail / N/A Choice
  • Mounting system secure * Pass / Fail / N/A Choice
  • Cabling and connectors secure * Pass / Fail / N/A Choice
  • DC isolators operate * Pass / Fail / N/A Choice
  • AC isolator operates * Pass / Fail / N/A Choice
  • Inverter display / no fault codes * Pass / Fail / N/A Choice
  • Labelling present * Pass / Fail / N/A Choice
  • Battery storage (if fitted) OK * Pass / Fail / N/A Choice
  • Monitoring connected * Pass / Fail / N/A Choice
  • Shading changes noted * Pass / Fail / N/A Choice

3. String readings repeats as needed

  • String reference * Text
  • Open circuit voltage Voc (V) Text
  • Short circuit current Isc (A) Text
  • Insulation resistance (megohms) Text
  • Result * Pass / Fail / N/A Choice

4. Result

  • Generation meter reading (kWh) Text
  • Recommendations Paragraph
  • Photo 1 Photo
  • Photo 2 Photo
  • Additional comments Paragraph
  • Engineer name * Text
  • Engineer signature * Signature
  • Date signed * Date
  • Customer name (print) Text
  • Customer signature Signature

Questions about this template

How often should solar panels be inspected?

An inspection every one to two years is typical for commercial systems, with visual checks more often. Follow the installer's or manufacturer's recommendations.

What do string readings show?

Comparing open-circuit voltage and short-circuit current between strings, and against expected values, shows faulty modules, connectors or shading.

What standard covers PV testing?

BS EN 62446-1 sets out the documentation, commissioning tests and inspection for grid-connected PV systems.