Heating System Commissioning Checklist template
Commissioning record for a new boiler or heat pump: flushing, inhibitor, controls, readings and handover to the customer.
Opens in a free trial with this form ready to use.
Download printable PDF (78 KB)Building Regulations Part L; manufacturer instructions
This template is provided as a starting point only. pro-Forms accepts no liability for the accuracy or suitability of its forms. Check every form with a suitably qualified person before using it in a live environment.
About this template
A commissioning record for a new boiler or heat pump. Record the installation, then confirm the system was flushed, inhibitor added, filter fitted, controls and compensation set, emitters balanced, condensate or defrost drainage and flue or ventilation correct and safety devices tested, with flow temperature, system pressure and combustion or COP readings.
The handover section records that controls were explained, instructions left, building control notified and the warranty registered, signed by the engineer and the customer.
What's on this form
Every field in the template, grouped as it appears on the phone. Required fields are marked *.
1. Installation
- Customer name * Text
- Site name Text
- Site address Paragraph
- Job reference Text
- Date of visit * Date
- Time on site Time
- Time off site Time
- Heat source make Text
- Heat source model Text
- Heat source serial number Text
- Heat source ID / barcode Barcode scan
- Heat source location Text
- Heat source * Gas boiler / Oil boiler / Air source heat pump / Ground source heat pump / Other Choice
2. Commissioning
- System flushed * Yes / No / N/A Choice
- Inhibitor added * Yes / No / N/A Choice
- Filter fitted * Yes / No / N/A Choice
- Time and temperature controls fitted * Yes / No / N/A Choice
- Weather / load compensation set * Yes / No / N/A Choice
- Radiators / emitters balanced * Yes / No / N/A Choice
- Condensate / defrost drainage correct * Yes / No / N/A Choice
- Flue / ventilation correct * Yes / No / N/A Choice
- Safety devices tested * Yes / No / N/A Choice
- Flow temperature setting (°C) Text
- System pressure (bar) Text
- Combustion CO (ppm) / heat pump COP Text
3. Handover
- Controls explained to customer * Yes / No / N/A Choice
- Manufacturer instructions left * Yes / No / N/A Choice
- Building control notification made * Yes / No / N/A Choice
- Warranty registered * Yes / No / N/A Choice
- Additional comments Paragraph
- Engineer name * Text
- Engineer signature * Signature
- Date signed * Date
- Customer name (print) Text
- Customer signature Signature
Questions about this template
Is commissioning a legal requirement?
Building Regulations Part L requires heating systems to be commissioned and the owner given information on how to operate them efficiently.
Who notifies building control?
Installers registered with a competent person scheme, such as Gas Safe or MCS, notify through the scheme. Otherwise, building control must be notified before work starts.
Why record flow temperature?
Lower flow temperatures improve efficiency, especially for heat pumps and condensing boilers. Recording the setting shows the system was set up properly.