Data Centre Site Survey mobile form preview
Prefabricated Data Centres Mobile form 4 sections · 33 questions Free

Data Centre Site Survey template

Pre-installation survey for a modular data centre: access, ground, power, fibre, cooling, planning and constraints.

Use this template free

Opens in a free trial with this form ready to use.

Download printable PDF (74 KB)

This template is provided as a starting point only. pro-Forms accepts no liability for the accuracy or suitability of its forms. Check every form with a suitably qualified person before using it in a live environment.

About this template

A pre-installation survey for a modular or prefabricated data centre. Record the delivery route and access restrictions, crane access, vehicle size limits, ground type, foundation needs, overhead obstructions and underground services, with photos.

Then record the utilities (power capacity and distance, generator need, fibre, water and earthing) and the requirements: IT load, racks, cooling approach, planning, security and any other constraints.

What's on this form

Every field in the template, grouped as it appears on the phone. Required fields are marked *.

1. Site

  • Customer * Text
  • Site name * Text
  • Site address * Paragraph
  • Survey date * Date
  • Surveyor * Text
  • Customer contact Text

2. Access and ground

  • Delivery route and access restrictions * Paragraph
  • Crane / HIAB access available? * Yes / No Choice
  • Maximum vehicle size Text
  • Ground type * Concrete slab / Tarmac / Hardcore / Soft ground / Unknown Choice
  • Foundation / plinth required? Yes / No Choice
  • Overhead obstructions Paragraph
  • Underground services known Paragraph
  • Access photo 1 Photo
  • Access photo 2 Photo
  • Access photo 3 Photo

3. Utilities

  • Available power supply (kVA) * Text
  • Distance to supply point (m) Text
  • Generator required? Yes / No Choice
  • Fibre / telecoms available? * Yes / No Choice
  • Distance to fibre point (m) Text
  • Water supply available? Yes / No / N/A Choice
  • Earthing arrangements known? Yes / No Choice

4. Requirements

  • Required IT load (kW) * Text
  • Number of racks Text
  • Cooling approach DX / Chilled water / Free air / In-row / To be confirmed Choice
  • Planning permission required? Yes / No / To be confirmed Choice
  • Security requirements Paragraph
  • Other constraints and notes Paragraph
  • Additional comments Paragraph
  • Surveyor name * Text
  • Surveyor signature * Signature
  • Date signed * Date

Questions about this template

Why survey access so carefully?

Modules are large and heavy. The delivery route, crane position and ground bearing capacity often decide whether a site is viable.

Do modular data centres need planning permission?

Often, yes, depending on size, location and how long they will stay. The survey records whether permission is needed so it can be checked early.

What does the IT load determine?

The IT load in kW drives the power supply, UPS, generator and cooling capacity the design needs.