Module Commissioning Checklist template
Site commissioning of an installed data centre module, from mechanical completion through integrated systems testing.
Opens in a free trial with this form ready to use.
Download printable PDF (74 KB)This template is provided as a starting point only. pro-Forms accepts no liability for the accuracy or suitability of its forms. Check every form with a suitably qualified person before using it in a live environment.
About this template
Site commissioning of an installed data centre module, from mechanical completion through to integrated systems testing. Check the module is level and secured, sealed, cabled, earthed and connected, then record energisation and tests: phase rotation, protection settings, UPS, generator changeover, cooling, fire suppression, BMS alarms, load bank and the integrated systems test.
Record the load bank load and duration, any outstanding items and sign-off from both the commissioning engineer and the customer.
What's on this form
Every field in the template, grouped as it appears on the phone. Required fields are marked *.
1. Details
- Project * Text
- Module reference * Text
- Site Text
- Date * Date
- Commissioning engineer * Text
2. Mechanical completion
- Module level and secured to foundation * Pass / Fail / N/A Choice
- Weather seals and roof complete * Pass / Fail / N/A Choice
- External cabling terminated * Pass / Fail / N/A Choice
- Earthing and bonding connected * Pass / Fail / N/A Choice
- Drainage and condensate connected * Pass / Fail / N/A Choice
- Fuel / water connections complete * Pass / Fail / N/A Choice
3. Energisation and tests
- Incoming supply phase rotation correct * Pass / Fail / N/A Choice
- Protection settings applied * Pass / Fail / N/A Choice
- UPS commissioning complete * Pass / Fail / N/A Choice
- Generator changeover tested * Pass / Fail / N/A Choice
- Cooling commissioning complete * Pass / Fail / N/A Choice
- Fire suppression armed and signed off * Pass / Fail / N/A Choice
- BMS alarms tested * Pass / Fail / N/A Choice
- Load bank test completed * Pass / Fail / N/A Choice
- Integrated systems test (power failure simulation) * Pass / Fail / N/A Choice
- Load bank test load (kW) Text
- Duration (hours) Text
4. Sign-off
- Outstanding items Paragraph
- Additional comments Paragraph
- Commissioning engineer name * Text
- Commissioning engineer signature * Signature
- Date signed * Date
- Customer name (print) Text
- Customer signature Signature
Questions about this template
What is an integrated systems test?
A test that proves all the systems work together, usually by simulating a mains failure with a load bank running, so the UPS, generator, cooling and controls respond as designed.
Why record protection settings?
Settings applied on site should match the design discrimination study. Recording them confirms they were set and checked.
Can outstanding items be tracked after handover?
Yes. They are listed on the record and can be followed up as separate tasks.